South Peak Wind

Completion Date : December 2019

Located on the south side of the Highwood Mountains, steep grades and mountainous terrain presented a great challenge to the field team as they battled through rocks, rattle snakes, and surprise inclement weather. They constructed 10 miles of access roads and graded areas for 29 new wind towers. The Rachel crew at South Peak was able to perform 240,000 CY of grading in the same amount of time we originally anticipated to perform 49,000 CY of grading! Still meeting the scheduled deadlines that we needed to achieve from the start of the project.

PROJECT HIGHLIGHTS

  • Grading for 29 new turbine sites which consisted of 240,000 CY of cut/fill
  • Grading and gravel for a new 7 acre laydown yard and O&M pad
  • Two weeks worth of rock excavation and removal from construction areas
  • Construction of 10 miles of new gravel access roads